Add a maintenance event

  1. Select the Maintenance View button or select (View | System Events) from the menu.

  2. Click the Add Event button or select the Edit | Add Event menu option.

     

  1. Accept the default Date/Time or specify the Date/Time of the event you are adding.

By default, the date/time will be 1 second after the event that is currently selected in the grid.

To set the Date/Time use the mouse to select the component of the date and time you want to change, then use the increment/decrement controls to change the selected component.

If the date and time you specify is invalid, the date/time will be set back to the default date/time.

  1. Select the Event you want to add from the drop down list of available events:

    Note: Not all event types are available for all views. Only the compatible events for the current view will be displayed in the list.

Depending on the Event selected from the drop down menu, the Data Elements section of the Add Event form will contain the required data to be configured. For example, for the Record non-critical fault against equipment event,

  1. Select a Status from the drop-down list provided.
  1. Click the Add Event button to add the event and keep the dialog open. If you have finished adding events, click the Add and Close button.
  2. To cancel (close the dialog without adding the event), click Close.