How is time categorised?

For each equipment unit, ALL time should be accounted for, 7 days per week, 24 hours per day, regardless of the mine schedule. Within this accounting you may have many different categories including forms of Idle, not scheduled to work etc.

Pitram builds a hierarchy of times. Working down from the top, all time is categorised according to:

  • Operating hours

    In general, the status of an equipment unit is considered to be Operating when the engine is running. (This may not be appropriate in cold climates where engines must be kept running at all times.)

  • Idle hours

    In general, the status of an equipment unit is considered to be Idle when the engine is turned off, but production could turn it on if required. (This may not be appropriate in cold climates where engines must be kept running at all times.)

  • Maintenance hours

    When an equipment unit is not available for production because it is in the maintenance division.

We can sub-group Maintenance hours into:

  • Preventative Maintenance (PM)

    Scheduled or planned maintenance; regular servicing.

  • Corrective Maintenance (CM)

    Unscheduled maintenance - usually a breakdown or failure while the equipment was operating.