Delays
Delay is an overall term for any activity that will prevent a piece of Equipment from completing a Task. Examples of Delays include:
-
Public holidays
-
Maintenance
-
Relocation
Mandatory properties of a Delay
Each Delay has the following mandatory properties:
-
A type to define it called the Process
-
An amount of time to complete it
The main Delays window provide global, reusable delays such as public holidays, weekends, known maintenance schedules, etc.
Add a new Delay
Click into “Delays” from the main header, right click “Delays” from the new window and click “Add New”.
- Active: Setting active/inactive controls every instance of this delay.
- Equipment: From a list select which pieces of equipment are relevant for the delay
- Process: Chosen from the list of inactive processes defined already
- Start/End: Controls the start/end time of the first occurrence of the delay
- Duration: Shows the length of time, cannot be controlled (controlled by Start/End)
- Occurrence: Set a recurrence of the delay in Hours/Daily/Weekly/Monthly/Years.
- Last Occurrence: Shows the last occurrence of the delay, cannot be controlled, used for reference/checking.