EquipChangedToStatusER
Automatic status change required: The carrier (the primary unit) has an emergency. All the associate attachments (the secondary units) are assigned an Idle status.
Reference data group: EquipChangedToStatusER When a primary piece of equipment is allocated to a particular status (typically a Down status), the status of the associated secondary equipment is changed.
Status Selection Mode: Manual Selection
In the following example, the status of secondary equipment will be changed if the associated primary equipment is allocated to one of the Down states. The status will be manually selected by the Control Room Operator from a subset of states.
It is assumed that the following active lists have been defined:
| Equipment Type | Active List | Items |
|---|---|---|
| Primary equipment | Carrier Equipment | Carrier1,Carrier2 |
| Secondary equipment | Attach Equipment | Attach1, Attach2 |
| East Locations | LocA, LocB | |
| Down States | Brakes, Engine |
To define a status change for secondary equipment:
- Working in the Reference Edit service of Dome, select Groups | Configuration Items | States | Equipment Status Rules | EquipChangedToStatusER on the navigation pane.
- Click Checkout on the header.
- Click New EquipChangedToStatusER on the header.
- Enter the following definitions:
| Option | Select |
|---|---|
| General | |
| Code | CARRIERDOWN |
| Description | Carrier Down: Trucks to Idle |
| Abbreviation | Carrier Down: Trucks to Idle |
| Attribute | |
| PrimaryEquipment* |
Carrier Equipment Select the appropriate active list from the list of Micromine Pitram | Equipment active lists. |
| SecondaryEquipment* |
Attach Equipment The units associated with the primary equipment. |
| Locations* |
East Locations Select the appropriate active list from the list of Micromine Pitram| Location active lists. |
| InitialEquipmentStates* |
Down States If the primary equipment is allocated to one of the states included in the above active list, it will trigger the status change of the secondary equipment. |
| StatusSelectionMode* |
Manual Selection The Control Room Operator will select the appropriate status from the active list defined by ManualSelectionStates, below. |
| ManualSelectionStates* |
Down States Select the appropriate status for the secondary unit: the hauling fleet, in this case. |
| AutomaticSelectionStatus* |
Idle If the StatusSelectionMode is any of the Automatic modes, Idle is the status that will be applied to the secondary equipment associated with the loader. |
- Click OK to save your settings.
- Click Checkin on the header.
- Click Publish on the navigation pane header.
- In the Publish dialog, click Publish. You will receive a message to say that publishing has been successful. Click OK to close the message.
* Required attribute
Wait till the version number of the reference edit group (EquipChangedToStatusER) is updated to the latest version.
In Data Acquisition
- Make sure that the status bar shows the latest version of the reference data.
- In the Equipment tab of the Data Groups pane, set the filter to Carrier Equipment.
- Right-click on Carrier1 and select Set Primary Status.
- Select Operating Time | Operating.
- Right-click on Carrier1 and select Allocate to Location. Select LocB.
- In the Equipment tab of the Data Groups pane, set the filter to Attach Equipment.
- Right-click on Attach1 and select Set Primary Status.
- Select Operating Time | Operating.
- Right-click on Attach1and select Allocate to Equipment.
- Select Carrier1.
- After some time, Carrier1 calls in to say the unit has engine problems. In the Equipment tab of the Data Groups pane, set the filter to Carrier Equipment.
- Right-click on Carrier1, select Set Primary Status and change the status from Operating to Down.
- You will receive a Status Change message similar to the following:
Equipment 'Carrier1' changed to status 'Down'. Select a new equipment status for the 'Attachments' allocated to this unit, or click Cancel to leave their status unchanged. Equipment Status: Engine.
- Click the drop-down arrow to select Engine from the Down States list for the attachment.
- Click OK to save the selection Attach1.
- Check that the status has been allocated to the attachment. In the Equipment tab of the Data Groups pane, select Attach1. Right-click and select Set Primary Status. The status is set to Engine.